Title 40 - PROTECTION OF ENVIRONMENT
Chapter I - ENVIRONMENTAL PROTECTION AGENCY (CONTINUED)


meaning accorded them under the applicable provisions of the Act. Act means the Clean Air Act, as amended by Pub.L. 101-549, 42 U.S.C. 7401, et seq. ...


this part shall apply to a pollutant-specific emissions unit at a major source that is required to obtain a part 70 or 71 permit if the unit satisfies all of...


the anticipated range of operations at a pollutant-specific emissions unit, monitoring under this part shall meet the following general criteria: (1) The owner or...


Sec. 64.3. The submission shall include the following information: (1) The indicators to be monitored to satisfy Sec.Sec. 64.3(a)(1)-(2); (2) The ranges...


(taking into account control devices to the extent appropriate under the definition of this term in Sec. 64.1) the applicable regulated air pollutant in an amount equal to...


shall act to approve the monitoring submitted by the owner or operator by confirming that the monitoring satisfies the requirements in Sec. 64.3. (b) In...


upon issuance of a part 70 or 71 permit that includes such monitoring, or by such later date specified in the permit pursuant to Sec. 64.6(d). (b) Proper maintenance. At...


the permitting authority may require the owner or operator to develop and implement a QIP. Consistent with Sec. 64.6(c)(3), the part 70 or 71 permit may specify an...


owner or operator must use monitoring that meets the requirements of this part, the owner or operator shall submit monitoring reports to the permitting authority in...


limitation or standard, or [[Page 16]] any existing monitoring, testing, reporting or recordkeeping requirement that may apply under federal, state, or...


referenced to this part from a subpart of 40 CFR part 60, 61, or 63 for which the owner or operator has chosen to comply with the provisions of this part as an...


referenced to this part from a subpart of 40 CFR part 60, 61, or 63 for which the owner or operator has chosen to comply with the provisions of this part as an...
...


Except as provided in paragraph (a)(2) of this section, the emission standards and established parameter ranges of this part shall apply at all times except during periods...


paragraph (b) of this section, the owner or operator of each regulated source subject to this part shall keep copies of notifications, reports, and records required by this...


subject to this subpart shall submit the following reports, as applicable: (1) A Notification of Initial Startup described in paragraph (b) of this section. ...


this section do not apply to Group 2A or Group 2B process vents. (b) Startup, shutdown, and malfunction plan. (1) Description and purpose of plan. The owner or operator of...


or reporting requirements - (1) Waiver application. The owner or operator may apply for a waiver from recordkeeping or reporting requirements if the regulated source...


of emission limitation. An owner or operator may request a determination of equivalence for an alternative means of emission limitation to the requirements of design,...


to the public of information provided to, or otherwise obtained by, the Administrator under this part shall be governed by part 2 of this chapter. With the exception...


preclude any State or political subdivision thereof from adopting and enforcing any emission standard or limitation applicable to a regulated source, provided that...


to the provisions of this part shall build, erect, install, or use any article, machine, equipment, or process to conceal an emission that would otherwise...


a State under sections 111(c) and 112(l) of the Act, the authorities contained in paragraph (b) of this section shall be retained by the Administrator and not transferred to...


reference in the corresponding sections noted. These incorporations by reference were approved by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and...


pursuant to this part, except as specified under Sec. 65.5(g)(1), shall be sent to the Administrator at the appropriate EPA Regional Office indicated in...


to control of regulated material emissions from surge control vessels, bottoms receivers, and other storage vessels where a referencing subpart references the use of...


and in subpart A of this part. If a term is defined in both subpart A of this part and in other subparts that reference the use of this subpart, the term shall have the...


owner or operator shall comply with the requirements of paragraph (b) or (c) of this section. (b) For each storage vessel storing a liquid for which the maximum true...


or operator who elects to control storage vessel regulated material emissions by using a fixed roof and an internal floating roof shall comply with the design requirements...


elects to control storage vessel regulated material emissions by using an external floating roof shall comply with the design requirements listed in paragraphs (a)(1) through...


elects to control storage vessel regulated material emissions by using an external floating roof converted into an internal floating roof shall comply with the internal floating...


[Code of Federal Regulations] [Title 40, Volume 13] [Revised as of January 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 40CFR65.46] [Page 50] TITLE 40 - PROTECTION OF ENVIRONMENT CHAPTER I - ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) PART 65 - CONSOLIDATED FEDERAL AIR RULE--Table of Contents Subpart C - Storage Vessels Sec. 65.46 Alternative means of emission limitation. Any person seeking permission to use an alternative means of compliance under this section shall use the procedures of Sec. 65.8. ...


subject to this subpart shall meet the requirements of Sec. 65.4, except the record specified in paragraph (b) of this section shall be kept as long as the storage vessel is...


a notification of initial startup be filed, then the content of the notification of initial startup shall at least include the information specified in Sec. 65.5(b) and...


[Code of Federal Regulations] [Title 40, Volume 13] [Revised as of January 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 40CFR65.60] [Page 52] TITLE 40 - PROTECTION OF ENVIRONMENT CHAPTER I - ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) PART 65 - CONSOLIDATED FEDERAL AIR RULE--Table of Contents Subpart D - Process Vents Sec. 65.60 Applicability. The provisions of this subpart and of subpart A of this part apply to regulated material emissions from process vents where a referencing subpart references the use of this subpart. ...


and in subpart A of this part. If a term is defined in both subpart A of this part and in other subparts that reference the use of this subpart, the term shall have the...


shall determine the group status (i.e., Group 1, Group 2A, or Group 2B) for each process vent. Group 1 process vents require control, and Group 2A and 2B process vents...


for the additional requirement for halogenated vent streams as provided in paragraph (b) of this section, the owner or operator of a Group 1 process vent shall comply...


and measurement methods for parameters that are used to determine group status. (b)(1) Sampling site. For purposes of determining TOC or HAP...


value greater than 1.0 without a recovery device shall monitor based on the approved plan as specified in Sec. 65.63(d). (b) As required in Sec. 65.63(a) and (c), an owner...


records of measurements, engineering assessments, and calculations performed to determine the TRE index value of the process vent according to the procedures of...


submit as part of the Initial Compliance Status Report specified in Sec. 65.5(d) the information recorded in Sec. 65.66(a), (b), and (c), as applicable. (b)...


to control of regulated material emissions from transfer racks where a referencing subpart references the use of this subpart for such emissions control. (b) If...


and in subpart A of this part. If a term is defined in both subpart A of this part and in other subparts that reference the use of this subpart, the term shall have the...


of the following equipment: (1) A closed vent system which routes the regulated material vapors to a control device as provided in Sec. 65.83(a)(1) and (2). ...


paragraph (a)(1), (2), (3), or (4) of this section. (1) 98 Percent or 20 parts per million by volume standard. Use a control device to reduce emissions of...


a transfer rack shall operate it in such a manner that emissions are routed through the equipment specified in either paragraph (a)(1) or (2) of this section. (1)...


determine compliance with Sec. 65.84(c)(2), the following procedures and equipment shall be used: (1) The pressure test procedures specified in Method 27 of appendix A...


control device pursuant to Sec. 65.83(a)(1) or (2) shall monitor the closed vent system and control device as required under the applicable paragraphs specified in...


the verification of U.S. Department of Transportation (DOT) tank certification or Method 27 of appendix A of 40 CFR part 60 testing required in Sec. 65.84(c) has...


and subpart A of this part apply to equipment that contains or contacts regulated material. Compliance with this subpart instead of the referencing subpart does not alter...


and in subpart A of this part. If a term is defined in both subpart A of this part and in other subparts that reference the use of this subpart, the term shall have the...


of paragraph (b) of this section do not apply to the performance standards of Sec. 65.111(b) for pressure relief devices or Sec. 65.112(f) for compressors operating...


this subpart [[Page 70]] shall be identified. Identification of the equipment does not require physical tagging of the equipment. For example, the equipment may...


operator of a regulated source subject to this subpart shall monitor regulated equipment as specified in paragraph (a)(1) of this section for instrument monitoring and...


detected as soon as practical but not later than 15 calendar days after it is detected except as provided in paragraph (d) or (e) of this section. A first attempt at repair...


(1) The owner or operator shall comply with this section no later than the implementation date specified in Sec. 65.1(f). (2) The use of monitoring data...


shall comply with this section no later than the implementation date specified in Sec. 65.1(f). (b) Leak detection. Unless otherwise specified in Sec. 65.102(b)...


Except as allowed in Sec. 65.102(b) or as specified in paragraph (e) of this section, the owner or operator shall monitor all connectors in each process unit initially...


The owner or operator shall comply with this section no later than the implementation date specified in Sec. 65.1(f). (b) Leak detection. (1) Monitoring...


liquid service; and instrumentation systems. (a) Compliance schedule. The owner or operator shall comply with this section no later than the...


owner or operator shall comply with this section no later than the implementation date specified in Sec. 65.1(f). (b) Compliance standard. Except during pressure releases...


this section no later than the implementation date specified in Sec. 65.1(f). (b) Seal system standard. Each compressor shall be equipped with a seal system...


comply with this section no later than the implementation date specified in Sec. 65.1(f). (b) Equipment requirement. Each sampling connection system shall...


comply with this section no later than the implementation date specified in Sec. 65.1(f). (b) Equipment and operational requirements. (1) Each open-ended valve...


process. (a) Compliance schedule. The owner or operator shall comply with this section no later than the implementation date specified in Sec. 65.1(f). ...


least the greater of either 10 percent of the pumps in a process unit (or plant site) or three pumps in a process unit (or plant site) leak, the owner or operator...


an alternative to complying with the requirements of Sec.Sec. 65.106 through 65.114 and Sec. 65.116, an owner or operator of a batch process that operates in regulated...


vent system and control device. Process units that are enclosed in such a manner that all emissions from equipment leaks are routed to a process or fuel gas system or collected...


one regulated source subject to the provisions of this subpart may comply with the recordkeeping requirements for these regulated sources in one recordkeeping system....


in paragraphs (a)(1) through (3) of this section has previously been submitted under the referencing subpart, each owner or operator shall submit an Initial...


The provisions of this subpart and of subpart A of this part (including the startup, shutdown, and malfunction provisions in Sec. 65.6) apply to routing emissions to...


All terms used in this subpart shall have the meaning given them in the Act and in subpart A of this part. If a term is defined in both subpart A of this part and in other...


(a) Storage vessel requirements. The owner or operator expressly referenced to this subpart from subpart C of this part shall comply with the following requirements,...


(a) Closed vent system equipment and operating requirements. The provisions of paragraph (a) of this section apply to closed vent systems collecting regulated...


to which storage vessel, transfer rack, or equipment leak regulated material emissions are routed. (a) Equipment and operating requirements...


used to control emissions from storage vessels or low-throughput transfer racks. (a) Nonflare control device equipment and operating requirements. The...


for equipment leaks only. (a) Equipment and operating requirements. (1) Owners or operators using a nonflare control device to meet the applicable requirements...


(a) Flare equipment and operating requirements. Flares subject to this subpart shall meet the performance requirements of paragraphs (a)(1) through (7) of this section. ...


(a) Incinerator equipment and operating requirements. (1) Owners or operators using incinerators to meet the 98 weight-percent emission reduction or 20 parts per million...


(a) Boiler and process heater equipment and operating requirements. (1) Owners or operators using boilers and process heaters to meet the 98...


control devices. (a) Absorber equipment and operating requirements. (1) Owners or operators using absorbers to meet the 98 weight-percent emission reduction or 20 parts...


devices. (a) Condenser equipment and operating requirements. (1) Owners or operators using condensers to meet the 98 weight-percent emission reduction or 20 parts...


as control devices. (a) Carbon adsorber equipment and operating requirements. (1) Owners or operators using carbon adsorbers to meet the 98 weight-percent...


adsorbers, and other recovery devices used as final recovery devices. (a) Final recovery device equipment and operating requirements. (1) Owners...


other halogen reduction devices. (a) Halogen scrubber and other halogen reduction device equipment and operating requirements. (1) An owner or...


(a) Other control device equipment and operating requirements. (1) Owners or operators using a control device other than one listed in Sec.Sec. 65.147 through 65.152...


for control and recovery devices. (a) General monitoring requirement applicability. (1) This section applies to the owner or operator of a...


flare compliance determination requirements. (a) Performance tests and flare compliance determinations. Where Sec.Sec. 65.145 through 65.155 require, or...


for control devices. (a) General procedures. Where Sec.Sec. 65.145 through 65.155 require, or the owner or operator elects to conduct, a performance test of...


and monitoring records. (a) Conditions of flare compliance determination records. Upon request, the owner or operator shall make available to the...


TRE index value determination records. (a) Availability of performance tests records. Upon request, the owner or operator shall make available to...


monitoring system data handling. (a) Continuous records. Where this subpart requires a monitoring device capable of providing a continuous record, the owner or...


recovery device monitoring records. (a) Monitoring system records. For process vents and high-throughput transfer racks, the owner or operator subject to this subpart...


(a) Closed vent system records. For closed vent systems, the owner or operator shall record the following information, as applicable: (1) For each closed vent system...


flare compliance determination notifications and reports. (a) Performance test and flare compliance determination reports. Performance test reports and...


Reports. (a) An owner or operator who elects to comply with Sec. 65.144 by routing emissions from a storage vessel or transfer rack to a process or to a fuel...


(a) Periodic reports shall include the reporting period dates, the total source operating time for the reporting period, and, as applicable, all information specified...


(a) Replacing an existing control or recovery device. As specified in Sec.Sec. 65.147(b)(2), 65.148(b)(3), 65.149(b)(3), 65.150(b)(2), 65.151(b)(2), 65.152(b)(2), or...


all proceedings for the assessment by EPA of a noncompliance penalty as provided by section 120 of the Clean Air Act. This penalty is designed to recover the economic...


which EPA will administer the noncompliance penalty provisions of section 120 of the Clean Air Act. Subpart A describes the scope of the part, defines key terms and states...


means the Clean Air Act, 42 U.S.C. 7401 et seq. as amended on August 7, 1977, except where the context specifically indicates otherwise. (b) Affiliated entity means a...


requirement, which could have been reviewed or [[Page 140]] challenged by means of the timely filing of an appropriate petition, no provision of this part or part 67...


of a penalty under section 120 are in addition to any other proceedings related to permits, orders, payments, sanctions or other requirements of State or Federal law....


litigation on the validity of these regulations shall not affect the authority of the Agency to issue notices of noncompliance or to conduct subsequent administrative...


shall issue a notice of noncompliance to the owner or operator of any source which he determines is in violation of applicable legal requirements and which is located in...


of noncompliance shall be in writing and shall include: (1) A specific reference to each applicable legal requirement of which the source is in violation; (2)...


(a) Within forty-five days after receiving a notice of noncompliance a source owner or operator shall either: (1) Calculate the amount of the penalty...


penalties shall be calculated in accordance with the Technical Support Document and the Manual. (b) Where the Administrator determines that no existing technology...


failure of a source owner or operator, who does not submit a petition for reconsideration as provided in Sec. 66.13(a)(2), to submit the information described in Sec....


upon concluding that a previously approved penalty calculation no longer is accurate, may: (1) Request, in writing, that the source owner or operator submit...


(a) A source owner or operator who would otherwise be subject to a noncompliance penalty will be exempted from that penalty during the period for which, and upon...


upon notice and opportunity for public hearing, exempt the owner or operator of any source from a penalty where he finds that a particular instance of noncompliance was...


(a) The Administrator may, upon notice and opportunity for a public hearing, exempt the owner or operator of a source if he finds with respect to a particular instance of...


to Sec. 66.31(a) (1), (2), (3), and (5) will cease to be effective upon termination or revocation of the order on which the exemption is based. (b) Exemptions...


may upon notice and opportunity for a hearing revoke an exemption granted to the owner or operator of any source at any time in accordance with paragraphs (b) and...


Decision on petitions. (a) Within thirty days after receiving a petition filed under Sec. 66.13, the Administrator shall notify the source owner or operator...


Procedure for hearings. (a) Except as provided in Sec.Sec. 66.32 and 66.33, hearings granted under Sec. 66.41(a)(3) shall be held as provided in Subpart J. (b)...


Final decision; submission of penalty calculation. Within forty-five days after EPA has notified the owner or operator of a source of the final Agency decision that it is...


(a) Within thirty days after receipt of a penalty calculation provided pursuant to Sec. 66.13(a)(1) or Sec. 66.43, the Administrator shall notify the source owner or operator...


forty-five days after receipt of notice under Sec. 66.51(a)(2) that the penalty has been recalculated by EPA, a source owner or operator who wishes to challenge EPA's...


a petition for reconsideration under Sec. 66.52 the Administrator shall: (a) Accept the penalty calculation of the owner or operator to the extent the...


66.53 shall be held as provided in subpart J. (b) The Presiding Officer at a hearing granted under Sec. 66.53 shall issue an initial decision within ninety days after...


submitted a petition pursuant to Sec. 66.13(a)(2), the first installment of the penalty shall be paid on the date six months after receipt of the notice of noncompliance. ...


part shall be made by wire transfer payable to the U.S. Treasury. Payments under this part which are less than $10,000 shall be made by cashier's or certified check made...


to make timely payment under Sec. 66.61 shall pay in addition to the penalty owed a quarterly nonpayment penalty. The nonpayment penalty shall be calculated as of the due date...


or operator of a source who is paying a noncompliance penalty under this part shall notify the Administrator in writing when he believes that the source has come into and...


days after the source owner or operator receives notification pursuant to Sec. 66.71(b) that it has achieved and is maintaining compliance with applicable legal requirements,...


Within forty-five days of receipt of a notice under Sec. 66.72(b) (2) a source owner or operator may petition for reconsideration in the form and manner provided in Sec....


after any adjustment of a noncompliance penalty under this Subpart has become administratively final: (1) Any deficiency owed by the source owner or operator shall be...


the courts by the source owner or operator includes and is limited to the following, provided the conditions of paragraph (b) of this section are met: (1) A notice...


The Supplemental Rules in this subpart, in conjunction with the Consolidated Rules of Practice (40 CFR part 22) shall govern all hearings held under this part. To the extent that...


of 40 CFR 22.08 (Consolidated Rules of Practice) shall become applicable when the Administrator grants a hearing. (b) Upon granting a hearing the Administrator...


designation shall notify the parties and shall, if appropriate, schedule a prehearing conference (or alternative procedures) under 40 CFR 22.19 and shall notify the parties of the...


to Sec. 66.42 EPA shall present evidence of violation of applicable legal requirements. The source owner or operator shall then present any rebuttal evidence. (b)...


(a) The Presiding Officer shall dispose of the issues raised in the hearing in a single written decision. Such decision shall terminate the Presiding...


procedures under which EPA will approve State programs for administering the noncompliance penalty program under section 120 of the Clean Air Act and will evaluate actions...


(a) The Administrator shall approve any program submitted by a State, or by a local governmental agency where no program has been submitted by a State, for administering...


to administer a section 120 program shall submit an application in writing to the Administrator describing its proposed program. All necessary supporting materials shall...


application submitted under Sec. 67.12 and shall: [[Page 153]] (1) Approve the program and delegate authority to the State to administer the program if...


a program approved pursuant to Sec. 67.13 may propose amendments to that program to the Administrator. The Administrator shall evaluate whether the State or local...


State with a program approved under Sec. 67.13 is not administering the program in conformity with the requirements of the Act or Sec. 67.11, or the delegation of authority,...


Federal notice of noncompliance to owners or operators of sources in States with approved programs. (a) The Administrator shall issue a notice of noncompliance to...


Administrator may, on his own initiative, review any determination by a State or its agent that a source owner or operator is or is not in compliance with applicable...


(a) In reviewing a decision that a source is in compliance with applicable legal requirements or entitled to an exemption for which no hearing conforming to Sec....


(a) In reviewing a decision that a source is in compliance with applicable legal requirements or is entitled to an exemption for which a hearing conforming to Sec....


on his own initiative or on petition review any initial, interim, or final penalty calculation made or approved by the State or local agent to determine whether it conforms...


(a) In reviewing a penalty calculation for which no hearing conforming to the requirements of Sec. 67.11(b)(4) was held, the Administrator shall evaluate the accuracy and...


(a) In reviewing a penalty calculation for which a hearing conforming to Sec. 67.11(b)(4) was held, the Administrator may invite comment on issues identified by him as...


petition process for adding or deleting substances to the list of regulated substances, the requirements for owners or operators of stationary sources concerning the...


of the following provisions is stayed from March 2, 1994 to December 22, 1997. (1) In Sec. 68.3, the definition of ``stationary source,'' to the extent...


unanticipated emission of a regulated substance or other extremely hazardous substance into the ambient air from a stationary source. Act means the Clean Air Act as amended...


a threshold quantity of a regulated substance in a process, as determined under Sec. 68.115, shall comply with the requirements of this part no later than the latest of...


stationary source subject to this part shall submit a single RMP, as provided in Sec.Sec. 68.150 to 68.185. The RMP shall include a registration that reflects all...


Program 2 or Program 3 shall develop a management system to oversee the implementation of the risk management program elements. (b) The owner or operator shall assign...


The owner or operator of a stationary source subject to this part shall prepare a worst-case release scenario analysis as provided in Sec. 68.25 of this part...


offsite consequences, the following endpoints shall be used: (1) Toxics. The toxic endpoints provided in appendix A of this part. (2) Flammables. The endpoints for...


and report in the RMP: (1) For Program 1 processes, one worst-case release scenario for each Program 1 process; (2) For Program 2 and 3 processes: (i)...


owner or operator shall identify and analyze at least one alternative release scenario for each regulated toxic substance held in a covered process(es) and at least one...


the RMP the population within a circle with its center at the point of the release and a radius determined by the distance to the endpoint defined in Sec. 68.22(a). ...


in the RMP environmental receptors within a circle with its center at the point of the release and a radius determined by the distance to the endpoint defined in Sec. 68.22(a)...


consequence analyses at least once every five years. (b) If changes in processes, quantities stored or handled, or any other aspect of the stationary source...


the offsite consequence analyses: (a) For worst-case scenarios, a description of the vessel or pipeline and substance selected as worst case, assumptions...


accident history all accidental releases from covered processes that resulted in deaths, injuries, or significant property damage on site, or known offsite...


(a) The owner or operator shall compile and maintain the following up-to-date safety information related to the regulated substances, processes,...


the hazards associated with the regulated substances, process, and procedures. The review shall identify the following: (1) The hazards associated with the process...


procedures that provide clear instructions or steps for safely conducting activities associated with each covered process consistent with the safety information for...


operating a process, and each employee newly assigned to a covered process have been trained or tested competent in the operating procedures provided in Sec. 68.52...


to maintain the on-going mechanical integrity of the process equipment. The owner or operator may use procedures or instructions provided by covered process...


evaluated compliance with the provisions of this subpart at least every three years to verify that the procedures and practices developed under the rule are adequate and...


incident which resulted in, or could reasonably have resulted in a catastrophic release. (b) An incident investigation shall be initiated as promptly as possible,...


otherwise noted. (a) In accordance with the schedule set forth in Sec. 68.67, the owner or operator shall complete a compilation of written process...


initial process hazard analysis (hazard evaluation) on processes covered by this part. The process hazard analysis shall be appropriate to the complexity of the process and...


written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety...


operating a process, and each employee before being involved in operating a newly assigned process, shall be trained in an overview [[Page 173]] of the...


this section apply to the following process equipment: (1) Pressure vessels and storage tanks; (2) Piping systems (including piping components such as valves); ...


written procedures to manage changes (except for ``replacements in kind'') to process chemicals, technology, equipment, and procedures; and, changes to stationary...


review for new stationary sources and for modified stationary sources when the modification is significant enough to require a change in the process...


evaluated compliance with the provisions of this subpart at least every three years to verify that procedures and practices developed under this subpart are adequate and...


incident which resulted in, or could reasonably have resulted in a catastrophic release of a regulated substance. (b) An incident investigation shall be initiated...


plan of action regarding the implementation of the employee participation required by this section. (b) The owner or operator shall consult with employees and...


for hot work operations conducted on or near a covered process. (b) The permit shall document that the fire prevention and protection requirements in 29 CFR 1910.252(a)...


maintenance or repair, turnaround, major renovation, or specialty work on or adjacent to a covered process. It does not apply to contractors providing...


(a) Except as provided in paragraph (b) of this section, the owner or operator of a stationary source with Program 2 and Program 3 processes shall comply with...


an emergency response program for the purpose of protecting public health and the environment. Such program shall include the following elements: (1) An...


noted. Redesignated at 61 FR 31717, June 20, 1996. This subpart designates substances to be listed under section 112(r)(3), (4), and (5) of the Clean Air Act,...


a regulated substance listed in Sec. 68.130 is present at a stationary source if the [[Page 177]] total quantity of the regulated substance contained in a process...


to modify, by addition or deletion, the list of regulated substances identified in Sec. 68.130. Based on the information presented by the petitioner, the...


[Code of Federal Regulations] [Title 40, Volume 13] [Revised as of January 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 40CFR68.125] [Page 179] TITLE 40 - PROTECTION OF ENVIRONMENT CHAPTER I - ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) PART 68 - CHEMICAL ACCIDENT PREVENTION PROVISIONS--Table of Contents Subpart F - Regulated Substances for Accidental Release Prevention Sec. 68.125 Exemptions. Agricultural nutrients. Ammonia used as an agricultural nutrient, when held by farmers, is exempt from all provisions of this part. ...


Sale as Fuel at Retail Facilities. A flammable substance listed in Tables 3 and 4 of Sec. 68.130 is nevertheless excluded from all provisions of this part when the substance...


Sale as Fuel at Retail Facilities. A flammable substance listed in Tables 3 and 4 of Sec. 68.130 is nevertheless excluded from all provisions of this part when the substance...
...


(a) The owner or operator shall submit a single RMP that includes the information required by Sec.Sec. 68.155 through 68.185 for all covered processes. The RMP...


provided in paragraph (b) of this section, an owner or operator of a stationary source required to report or otherwise provide information under this part may make a claim...


owner or operator claiming that information is confidential business information must substantiate that claim by providing documentation [[Page 186]] that...


summary that includes a brief description of the following elements: (a) The accidental release prevention and emergency response policies at the stationary source; ...


form and include it in the RMP. The form shall cover all regulated substances handled in covered processes. (b) The registration shall include the following data: ...


the RMP information: (1) One worst-case release scenario for each Program 1 process; and (2) For Program 2 and 3 processes, one worst-case release scenario to represent...


[Code of Federal Regulations] [Title 40, Volume 13] [Revised as of January 1, 2003] From the U.S. Government Printing Office via GPO Access [CITE: 40CFR68.168] [Page 187] TITLE 40 - PROTECTION OF ENVIRONMENT CHAPTER I - ENVIRONMENTAL PROTECTION AGENCY (CONTINUED) PART 68 - CHEMICAL ACCIDENT PREVENTION PROVISIONS--Table of Contents Subpart G - Risk Management Plan Sec. 68.168 Five-year accident history. The owner or operator shall submit in the RMP the information provided in Sec. 68.42(b) on each accident covered by Sec. 68.42(a). ...


or operator shall provide in the RMP the information indicated in paragraphs (b) through (k) of this section. If the same information applies to more than one covered...


operator shall provide the information indicated in paragraphs (b) through (p) of this section. If the same information applies to more than one covered process, the owner...


the RMP the following information: (1) Do you have a written emergency response plan? (2) Does the plan include specific actions to be taken in response to...


in the RMP the certification statement provided in Sec. 68.12(b)(4). (b) For all other covered processes, the owner or operator shall submit in the RMP a...


in paragraph (b) of this section and submit it in a method and format to a central point specified by EPA prior to June 21, 1999. (b) The owner or operator of...


The owner or operator shall maintain records supporting the implementation of this part for five years unless otherwise provided in subpart D of...


G of this part shall be available to the public under 42 U.S.C. 7414(c). (b) The disclosure of classified information by the Department of Defense or other Federal...


(a) These requirements apply to any stationary source subject to this part 68 and parts 70 or 71 of this chapter. The 40 CFR part 70 or part 71 permit for the...


and enforcement of the Act, the implementing agency shall periodically audit RMPs submitted under subpart G of this part to review the adequacy of such RMPs and...


Air Act (``CAA'') and a petition submitted by the Governor of Guam (``Petition''), the Administrator of the Environmental Protection Agency (``EPA'')...


the initial eighteen month exemption provided under section 325(b) of ``the Act'', the Administrator of the Environmental Protection Agency (EPA) exempts the Guam Power...


response to a petition submitted by the Governor of Guam and pursuant to section 325(a) of the Clean Air Act (Act), the Administrator of the United States EPA (EPA) grants...


response to a petition submitted by the Governor of American Samoa (American Samoa) and pursuant to section 325(a) of the Clean Air Act (Act), the Administrator of the...


In response to a petition submitted by the Governor of The Commonwealth of the Northern Mariana Islands (CNMI) and pursuant to section 325(a) of the Clean Air...


the Clean Air Act and a petition submitted by the Governor of the Virgin Islands, an exemption to section 123 of the Clean Air Act is granted to the Hess Oil Virgin...


use only in Alaska and is used only in Alaska, is exempt from the sulfur standard of 40 CFR 80.29(a)(1) and the dye provisions of 40 CFR 80.29(a)(3) and 40 CFR...


with the requirements of title V of the Clean Air Act (Act) (42 U.S.C. 7401, et seq.). These regulations define the minimum elements required by the Act for...


meaning accorded them under the applicable requirements of the Act. Act means the Clean Air Act, as amended, 42 U.S.C. 7401, et seq. Affected source shall have...


the following sources: (1) Any major source; (2) Any source, including an area source, subject to a standard, limitation, or other requirement under section 111...


the following sources: (1) Any major source; (2) Any source, including an area source, subject to a standard, limitation, or other requirement under section 111...
...


in accordance with this section. (1) Timely application. (i) A timely application for a source applying for a part 70 permit for the first time...


limitations and standards, including those operational requirements and limitations that assure compliance with all applicable requirements at the time of permit issuance. ...


only if all of the following condition have been met: (i) The permitting authority has received a complete application for a permit, permit modification, or permit...


the permitting authority provide to the Administrator a copy of each permit application (including any application for permit modification), each proposed permit, and each...


annual fees, or the equivalent over some other period, that are sufficient to cover the permit program costs and shall ensure that any fee required by this section will be...


70 program, or a required revision thereto, in conformance with the provisions of Sec. 70.4, or if an interim approval expires and the Administrator has not approved a...


70 program, or a required revision thereto, in conformance with the provisions of Sec. 70.4, or if an interim approval expires and the Administrator has not approved a...
...


(a) This part sets forth the comprehensive Federal air quality operating permits permitting program consistent with the requirements of title V of the Act (42 U.S.C. 7401...


in this section, terms used in this part retain the meaning accorded them under the applicable requirements of the Act. Act means the Clean Air Act, as amended,...


are subject to the permitting requirements under this part: (1) Any major source; (2) Any source, including an area source, subject to a standard, limitation,...


and enforce a full or partial operating permits program for a State (excluding Indian country) in the following situations: (1) A program for a State meeting...


shall submit a timely and complete permit application in accordance with this section. (1) Timely application. (i) A timely application for a source which does...


shall submit a timely and complete permit application in accordance with this section. (1) Timely application. (i) A timely application for a source which does...
...


A permit, permit modification, or renewal may be issued only if all of the following conditions have been met: (i) The permitting authority has received a...


becomes effective in a State or within Indian country, the permitting authority shall provide notice of each draft permit to any affected State, as defined in Sec. 71.2...


pay annual fees, or the equivalent over some other period, that are sufficient to cover the permit program costs, in accordance with the procedures described in...


delegate, in whole or in part, with or without signature authority, the authority to administer a part 71 operating permits program to a State, eligible Tribe, local,...


of this section shall apply to all permit proceedings. Notwithstanding the preceding sentence, paragraphs (a) through (h) and paragraph (j) of this section shall not apply...


any fee or filing requirement; any duty to allow or carry out inspection, entry, or monitoring activities; or any regulation or order issued by the permitting...


a limited, Federal, title V, permit program to establish alternative emission limitations for early reductions sources that have demonstrated qualifying reductions of...


are given the same meaning as in the Act or in subpart D of part 63 of this chapter. Act means the Clean Air Act, as amended, 42 U.S.C. 7401, et seq. ...


an owner or operator of an existing source who is seeking a compliance extension under section 112(i)(5) of the Act and who, pursuant to part 63, subpart D, of this chapter,...


and an alternative emission limitation under this subpart, the owner or operator of an early reductions source shall file a complete permit application with the...


this subpart shall include the following elements: (1) Alternative emission limitation. An annual alternative emission limitation for hazardous air pollutants from...


A permit or permit revision may be issued only if all of the following conditions have been met: (i) The Administrator has received a complete application for a permit...


of draft permits, initial permit issuance, permit revisions, and granted appeals, shall provide adequate procedures for public participation, including...




PEO7.com 23945 Calabasas Rd. Suite 106, Calabasas, CA 91302 818-222-4572 cs@peo7.com
SiteMap  | Employee Leasing  | Exploring the Possibilities  | What is Employee Leasing  | Why use a Peo  | Free Advice  | Benefits to  Employees  |  Responsibilities of PEO  | Benefit Package  | HR Management  | Pre-Employment Screening  | The Issue of Control  |  Future of PEO |  Request For Proposal (RFP)  | Contact Us  | Peo Resources |  Terms of Service | FAQ